What is the overall cost of the renovation?
Current projected cost is $50 million.
How long will the project take from start to finish?
The renovation is expected to take two years and will be done in phases to avoid relocation and interruption of SDSU events.
How will you celebrate and acknowledge the rich history of Frost Arena in the new facility?
Plans are in place to showcase the past 50 years of Frost Arena in a designated, fan-interactive space within the renovated facility.
What happens to the Stanley J. Marshall Center?
The Stanley J. Marshall Center name will remain in place and the space will continue to serve as the home of administrative offices and select support facilities for the athletic department.
How can I support the project?
In collaboration with the SDSU Foundation and athletic development team, donors can make gifts to this project. You may view naming opportunities along with contact information on BackTheJacks.com.
What is the proposed capacity?
Capacity is set for 5,500 spectators in the renovated arena.
What’s the fundraising status of the project?
There has been very good donor interest in the project. With a significant lead gift now in place, we anticipate discussions for other seven- and six-figure commitments to move forward. There are additional fund raising goals that need to be met before the university seeks Board of Regents and Legislative approval.
When can I purchase tickets, premium seating or suites?
A fan survey will be conducted in the near future that will layout amenities and features. Once finalized, a comprehensive ticketing plan will be available for season ticket holders, Jackrabbit Club members, corporate sponsors and new supporters of the project. We also predict a seating reallocation to take place in either the spring of 2022 or 2023.Â
Who is the general contractor and architect for the project?
Henry Carlson is the general contractor for the project. EAPC Architects Engineers is managing the architectural renderings and specifications.